Fairview P9390GSI – Engine Install & Compressor Overhaul

Project Overview:

The Fairview field, operated by Santos in Queensland’s Surat and Bowen Basins, includes four compression facilities with a total capacity of approximately 588 TJ per day. To minimise downtime, Santos had prepared a “spare” Waukesha P9390GSI engine for rapid replacement at the CS2 facility. Altrad (formerly Valmec) was engaged to execute the engine installation and overhaul an Ariel JGK-4 compressor, ensuring continuity in production while maintaining high safety and quality standards.

Scope:

  • Installation and commissioning of a zero-hour rebuilt Waukesha P9390GSI reciprocating gas engine.
  • Major overhaul of an Ariel JGK-4 reciprocating gas compressor.

Outcomes:

  • Completed the project within the 10-day schedule, significantly reducing potential downtime compared to traditional methods.
  • Conducted all works within the scheduled timeframe and budget, with zero incidents.
  • Simultaneous execution of the engine replacement and compressor overhaul to minimise downtime required precise planning and coordination.
  • Removal and reinstallation of the facility’s roof to facilitate engine lifting during ongoing works.
  • Strict adherence to heat stress and fatigue management plans, as the work was conducted in extreme temperatures exceeding 40°C.
  • Reinforced Altrad’s capability to deliver critical maintenance projects efficiently and safely under challenging conditions.
  • Ensured production continuity for Santos, supporting its LNG supply chain.
Client

Santos

Location

Fairview, Queensland

Duration

1.5 weeks Completion: December 2019